Skip to Content

The Week Ahead

Campus Development: The Week Ahead

The Estates Directorate will do everything possible to manage the impact of works and we hope that they do not cause you too much inconvenience. If you have any comments regarding noise, please contact us on ext.5005 or email estates@qub.ac.uk.

The path leading to the McClay Library
03 March 2025
Main Site, Elmwood Avenue, PEC and Titanic Quarter

Major Works projects and Minor Works projects will be taking place this week. Major Works projects include the new Seamus Heaney Centre and One Elmwood. Minor Works projects include work at Lanyon façade, 92 Lisburn Road, Maths & Physics Teaching Centre, Whitla Hall and PEC. For more information, please see the drop-down menus below.

  • Major Projects

    NEW SEAMUS HEANEY CENTRE (38 – 40 UNIVERSITY RD & 3 MOUNT CHARLES)

    • Limited contractor attendances will continue throughout March 2025 to address snags.
    • Roofing works are anticipated in early March 2025 with possible access on the Mount Charles side of the building. As such there will be temporary barriers in place around roof access plant and equipment.
    • Some minor external works to the building elevation and external landscaping are anticipated. Localised pedestrian barriers will be in place during working hours.

    Possible Impact: Some noise, personnel movement and delivery of materials or plant, temporary restrictions to parking and pedestrian access.

    ONE ELMWOOD

    • The installation of replacement light fittings and controls in specific rooms throughout One Elmwood. The works are programmed for completion in April 2025.

    Possible impact: Some staff will be required to relocate for a limited period while lights in their normal working area are replaced. Limited low level noise.

  • Minor Works and Planned Maintenance

    LANYON BUILDING FAÇADE LIGHTING UPGRADE

    • Replacement of existing lighting. Works are due to be completed by end of March 2025.

    Possible Impact:  Increased activity, noise, personnel movement and delivery of materials.

    WHITLA HALL - ROOF REPAIRS & SOLAR PV PANEL INSTALLATION 

    • Fitting of new asphalt layers followed by PV panel installation. Works are due to be completed by the end of March 2025.

    Possible Impact:  Increased activity, noise, personnel movement and delivery of materials.

    MATHS & PHYSICS TEACHING CENTRE – SOLAR PV PANEL INSTALLATION 

    • PV panel installation to be fitted on building roof. Works are due to be completed by the end of March 2025.

    Possible Impact:  Increased activity, noise, personnel movement and delivery of materials.

    92 LISBURN ROAD

    • Internal refurbishment work on all four floors.  Works are due to be completed by the middle of April 2025.

     Possible Impact: Noise from power tools and construction workers in the areas.

    PEC - UPGRADE OF CCTV ON ALL FLOORS

    • Installation of electrical infrastructure throughout PEC to support new cameras. The works are due to be completed in March 2025.

    Possible Impact:  Increased activity, noise, personnel movement and delivery of materials.

03 March 2025
Health Sciences and Royal Victoria Hospital Campuses

No Major Works projects will be taking place this week. Minor Works projects will be taking place this week. Minor Works projects include work at the MBC, Patrick G Johnston Centre for Cancer Research (PGJCCR) and Royal Victoria Hospital (RVH). For more information, please see the drop-down menus below.

  • Major Projects

    There are no major project works taking place this week.

  • Minor Works and Planned Maintenance

    MBC - INFRASTRUCTURE WORKS TO FACILITATE EV CAR CHARGERS

    • Installation of containment for power supply cables from building across car park to EV charger location. Works are due to be completed by the end of March 2025.

    Possible Impact: Increased external activity, dust, noise, vibration, personnel movement and delivery of materials.

    RVH CLINICAL SCIENCE A - REPLACEMENT OF SWITCHBOARD

    • Infrastructure works to replace main electrical switchgear. Works are due to be completed by the end of April 2025.

    Possible Impact: Increased external activity, dust, noise, vibration, personnel movement and delivery of materials.

    PGJCCR –FORMER DARK ROOM 0G.022

    • Refurbishment of former Dark Room area, including the removal of a revolving door, to create a new office. Works are due to be completed by early March 2025.

    Possible Impact:  Noise from power tools, dust from works and increased workmen traffic.

    MBC – BSU (FLOORS 7 & 8)

    • Upgrade of staff welfare facilities (kitchen, toilets etc) on floors 7 and 8. Works are due to be completed by late April 2025.

    Possible Impact: Noise from power tools and increased personnel in area.

    MBC – HAMMERHEAD ROOF

    • Repairs to Hammerhead roof. Works are due to be completed by the middle of March 2025.

    Possible Impact: Noise from power tools, dust from works and increased personnel in area. Use of Mobile Elevating Work Platforms (MEWPs) which will block car parking spaces and the side entrance door.

David Keir Building
03 March 2025
Keir, Riddel Hall, Elms and Windsor Park

Major Works projects and Minor Works projects will be taking place this week. Major Works projects include work in the David Keir Building (DKB). Minor Works projects include work in the David Keir Building (DKB), SARC, Windsor Park, Ashby Tower and Queen’s Business School. For more information, please see the drop-down menus below.

  • Major Projects

    DKB - NATURAL AND BUILT ENVIRONMENT (NBE)

    The enabling works for the project have resulted in the identification of a limited area of RAAC structural flooring.

    Following precautionary closure of the relevant areas, a structural assessment has confirmed that it is acceptable to reoccupy the basement and lower ground levels of DKB Block 03, provided the Ground level remains vacant. Safety Services have inspected and confirmed that mitigation measures to protect students, staff and visitors in the quad are acceptable. Signage and temporary barriers have been amended to allow access as agreed and detailed.

    Access to the Level 01 Waste Water Lab will remain restricted to essential works, with limited numbers of staff for restricted hours only.

    Remedial works design has been developed by the appointed Structural Engineers, and will comprise of propping the first floor from below, resulting in the Ground Floor remaining vacant for the duration of the remedial works. 

    Delivery of the new NBE Civil Engineering Studio refurbishment will commence post completion of remedial works, this will result in the Ground Floor accommodation not being operational for a significant portion of 2025.

    Possible Impact: Restricted access as detailed above.

  • Minor Works and Planned Maintenance

    QUEEN’S BUSINESS SCHOOL STUDENT HUB - INFRASTRUCTURE WORKS TO FACILITATE EV CAR CHARGERS

    • Installation of containment for power supply cables from building across carpark to EV charger location. Works are due to be completed by the end of March 2025.

    Possible Impact: Increased external activity, dust, noise, vibration, personnel movement, and delivery of materials

    SONIC ARTS RESEARCH CENTRE (SARC)

    • Internal refurbishment work on second and third floors.  Works are due to be completed in late March 2025.

     Possible Impact: Noise from power tools and construction workers in the areas.

    WINSDOR PARK - BLOCKS 36 & 38

    • Upgrade of existing staff accommodation. The work includes replacement of kitchen cupboard doors, sinks, taps, worktops, installation of new appliances, lighting upgrade to LED, replacement boiler and upgrading of heating controls to form one zone. Works are due to be completed by the end of March 2025.

    Possible Impact: Increased activity, dust, noise, vibration, personnel movement and delivery of materials.

    DKB – REFURBISHMENT OF OFFICE 01.411 

    • Strip out and recommissioning of existing office. The works include minor strip out of existing furniture, painting, flooring, new door, data and power alterations and replacement of lights. Works are due to be completed by the middle of April 2025.

    Possible Impact: Increased activity, dust, noise, vibration, personnel movement and delivery of materials.

    DKB – REFURBISHMENT OF OFFICE 02.118  

    • Strip out and recommissioning of existing office. The works include minor strip out of existing furniture, painting, flooring, new door, data and power alterations, removal of dead legs, firestopping and replacement of lights. Works are due to be completed by the middle of April 2025.

    Possible Impact: Increased activity, dust, noise, vibration, personnel movement and delivery of materials.

    ASHBY TOWER - NORTH AND SOUTH UPPER STAIRWELLS 

    • Painting of north and south upper stairwells. Works are due to be completed by the end of March 2025.

    Possible Impact: Increased activity, dust, noise, personnel movement and delivery of materials. 

03 March 2025
Belfast Region City Deal

Belfast Region City Deal project works will be taking place this week on the new Institute of Research Excellence for Advanced Clinical Healthcare (iREACH Health) site and Momentum One Zero (M1.0). For more information, please see the drop-down menus below.

  • Belfast Region City Deal

    INSTITUTE OF RESEARCH EXCELLENCE FOR ADVANCED CLINICAL HEALTHCARE (iREACH HEALTH)

    • Enabling works to the Russel Court tower block site and car park site on the opposite side of Lisburn Road. Works include site set-up, temporary hoarding, asbestos removal, soft strip and phased demolitions. Enabling Works are estimated to be due for completion in March 2025.

    Possible Impact: Potential for noise from power, tools, hammers, generator etc.

    • Contractor deliveries to site.

    Possible Impact: Site access is being manned by contractor’s staff overseeing deliveries. Some noise and vibration from manoeuvring machines.

    MOMENTUM ONE ZERO (M1.0)

    • Enabling works at Queen’s Titanic Quarter QTQ (formally ECIT) will commence on Monday 17 February 2025 and is due for completion by Friday 11 April 2025. Works include the diversion of the existing NIE and NI Water supplies, relocation of the existing gas meter and works to the existing foul sewer.

    Possible Impact: Potential for noise from the civil engineering works.  Disruption to existing car parking as access to the contractor’s compound (located on the existing stone area at the rear of the car park) will be through the existing car park. All the civil engineering works will take place within the contractor’s compound.