Week Ahead 04 Jan 2021

21 & 28 December 2020
Health Sciences and Royal Victoria Hospital Campuses

There will be no works in progress over the Christmas/New Year period (19 December 2020 – 03 January 2021 inclusive) apart from limited work in Clinical Sciences A room 0G.016 on the 21 and 22 December 2020. Works will resume on Monday 04 January 2021. For more information, please see the drop-down menus below.

David Keir Building
21 & 28 December 2020
Keir/Ashby/Lennoxvale/Riddel Hall

There will be no works in progress over the Christmas/New Year period (19 December 2020 – 03 January 2021 inclusive). Works will resume on Monday 04 January 2021. For more information, please see the drop-down menus below.

The path leading to the McClay Library
21 & 28 December 2020
Main Site and Elmwood Avenue

There will be no works in progress over the Christmas/New Year period (19 December 2020 – 03 January 2021 inclusive) apart from the Student Centre where contractors will be onsite until Tuesday 22 December 2020. Works will resume on Monday 04 January 2021. For more information, please see the drop-down menus below.

Campus Development: The Week Ahead

The Estates Directorate will do everything possible to manage the impact of works and we hope that they do not cause you too much inconvenience. If you have any comments regarding noise, please contact us on ext.5005 or email estates@qub.ac.uk.

  • Major Projects

    MANAGEMENT SCHOOL, RIDDEL HALL

    There will be no works in progress over the Christmas/New Year period. The building contractors will finish on Friday 18 December 2020 and start back on Monday 04 January 2021.

  • Minor Works and Planned Maintenance

    MAIN BLOCK, RIDDEL HALL 

    There will be no works in progress over the Christmas/New Year period. The building contractors will finish on Friday 18 December 2020 and start back on Monday 04 January 2021.

  • Major Projects

    WWIEM VENTILATION UPGRADE

    There will be no works in progress over the Christmas/New Year period. The building contractors will finish on Friday 18 December 2020 and start back on Monday 04 January 2021.

     

    CLINICAL SCIENCES A & B

    The work on site will generally cease on 18 December 2020. There will, however, be some limited works in Clinical Sciences A room 0G.016 on 21 and 22 December 2020. The building contractors will finish on Tuesday 22 December 2020 and start back on Monday 04 January 2021.

     

     

  • Minor Works and Planned Maintenance

    MBC TOILET REFURBISHMENT

    The toilet refurbishments have been completed.

  • Major Projects

    McCLAY LIBRARY REFURBISHMENT PHASE 3

    There will be no works in progress over the Christmas/New Year period. The building contractors will finish on Friday 18 December 2020 and start back on Monday 04 January 2021.

     

    STUDENTS CENTRE

    The building contractors will finish on Tuesday 22 December 2020 and start back on Monday 04 January 2021.

     

  • Minor Works and Planned Maintenance

    71 – 75 UNIVERSITY ROAD

    There will be no works in progress over the Christmas/New Year period. The building contractors will finish on Friday 18 December 2020 and start back on Monday 04 January 2021.

     

    LANYON BUILDING

    The internal refurbishment of the stairwell (leading to Registrar’s Offices) has been completed.

     

    MUSIC BUILDING

    Replacement of carpets and installation/replacement of air conditioning have been completed.